M5 J10 slip roads to close for about two years from early 2027
The £210m main contract for the £372m M5 junction 10 rebuild near Cheltenham has been awarded, and the existing slip roads are due to close from early 2027.

The main construction contract, worth £210m, has been awarded for the £372m rebuild of M5 junction 10 near Cheltenham. According to our UKcheckpoints page, citing Gloucestershire County Council and National Highways, the existing northbound on-slip and southbound off-slip are due to close for around two years from early 2027.
The M5 itself stays open. Only access at J10 is affected, but that access goes completely, so Cheltenham drops will mean a longer run via J9 or J11.
Diversions
- Northbound: the council's diversion is the A4019, A38 and A438, rejoining at J9.
- Southbound: leave at J11, then take the A40 eastbound, A4013 and A4019.
The new layout will have four slip roads and a roundabout on two new bridges. Withybridge Lane will also close at times.
The dates and diversions are the council's current plans, and it says more detail will follow before the closures start. If you run into west Cheltenham, it's worth checking your delivery and collection routes now and allowing extra time once the work begins.